The primary objective of this project was to purchase and deliver 200 managed Chromebooks to a newly established middle school. The key goal was to balance quality with a limited budget while ensuring the devices supported seamless student learning. Additionally, the project aimed to complete onsite setup within three days, ensuring proper enrollment and compliance with Board of Education standards.

Deliverables

  • 200 Managed Chromebooks:

    Acquired and configured to meet the educational needs of the students.

  • Onsite Setup and Enrollment:

    Completed within three days, including device configuration, enrollment, and compliance checks.

  • Training and Support:

    Provided to the school's staff for ongoing management and troubleshooting.

Challenges

  • Software Deployment Issues:

    Although the software was successfully tested prior to the site visit, it failed to deploy onsite, necessitating manual enrollment of several Chromebooks.

  • Time Constraints:

    The project required completion within a tight three-day window.

  • Budget Limitations:

    Ensuring high-quality devices and extended warranties while staying within the limited budget.

Results

The project was completed ahead of schedule and within the allocated budget. The successful deployment and setup of the Chromebooks resulted in high satisfaction from the stakeholders. This success led to an additional networking project for the school, highlighting the effectiveness and reliability of the project management approach.

  • Thorough Pre-Deployment Testing:

    Emphasized the importance of extensive testing in environments similar to the deployment site to avoid unforeseen issues.

  • Flexible Risk Management:

    Demonstrated the value of having a robust risk management plan, including budget cushions and extended timelines.

  • Team Collaboration:

    Highlighted the importance of having multiple team members onsite to quickly address challenges.

  • Stakeholder Communication:

    Reinforced the need for clear and continuous communication with stakeholders to manage expectations and ensure satisfaction.

More Projects

Milestone State Testing

The Milestones Testing project successfully met all deliverables on time and within budget.

Inaugural Knowledge Base

The implementation of the Knowledge Base significantly enhanced employee retention and client satisfaction.

Chromebook Deployment

The Chromebook Deployment project was completed earlier than expected leading to the Stakeholders requesting another major project.

Executive Laptop Replacement

The Laptop Replacement project successfully provided and configured a new laptop for the executive resulting in additional laptop purchases and contract renewals.

Greyhound Acclimation

Ensure the smooth transition and adjustment of retiring racing Greyhounds arriving monthly from overseas.

Everto Vending

The Everto Vending project established a low-risk vending business that generates consistent monthly revenue with minimal overhead.